Government Hospital Avadi, Thiruvallur
August 2021The Medical Camp was conducted by the Hospital Authority to vaccinate the labours & staffs of the construction project. (dt. 01.08.2021)
August 2021Project Director & JICA Representative - Site Visited on 02.08.2021
August 2021Detailed project display boards in Tamil & English language are provided in the site. (dt. 14.08.2021)
August 2021Safety meeting conducted by the Safety Engineer for the site labours. (dt. 14.08.2021)
August 2021SE & AEE (Electrical), PWD visited the site for monitoring quality and progress of construction works. (dt. 23.08.2021)
August 2021AEE (Electrical), PWD & AE (Electrical), PWD visited the site for joint inspection. (dt. 28.08.2021)
August 2021De-shuttering the columns and covered by gunny bags for curing Dt. 05.08.2021
August 2021Column concrete works under progress Dt. 07.08.2021
August 2021Shuttering for mid landing beam under progress Dt. 13.08.2021
August 2021Made centring plates for staircase and laying for staircase slab Dt. 17.08.2021
September 2021Shuttering work completed for ground floor roof level. (dt. 02.09.2021)
September 2021Mr. Duglus, AEE, PWD visited site and inspected the Electrical lines and conduits fixed in ground floor roof slab before pouring concrete. (dt. 09.09.2021)
September 2021Reinforcement and shuttering supports for roof slab work inspected consultant and PWD officials. (dt. 09.09.2021)
September 2021Completed Ground floor roof slab concrete works. (dt. 15.09.2021)
September 2021Safety meeting conducted by the Safety Engineer for the site labours. (dt. 17.09.2021)
September 2021SE-PWD, EE-PWD, AEE – PWD visited site for general inspection of work progress. (dt. 29.09.2021)
September 2021Preparation and fixing ramp column box for column lifting up to ground floor roof beam bottom level Dt. 02.09.2021
September 2021Reinforcement cutting, bending and laying for ground floor roof slab in lobby area Dt. 09.09.2021
September 2021Pouring RCC concrete for ground floor roof beam, slab, Staircase flight 3 and Ramp flight up to first floor level. Dt. 14.09.2021
September 2021