TNHSP Logo
044-24345992 , 044-24335993 pdtnhsp@gmail.com
TNHSP Logo

Govt. Hospital Tirunelveli

Home > Govt. Hospital Tirunelveli

Government Hospital Kandiyaperi, Tirunelveli

calendar August 2021
Joint Site Inspection with DTCP Joint Director, PWD, Consultants & Contractor on 05.08.2021
calendar August 2021
Grade concrete pouring work has been completed on 10.08.2021.
calendar August 2021
EE, PWD visited the site for monitoring quality and progress of construction works. (Dt. 13.08.2021)
calendar August 2021
Environment upgradation activity: 21 numbers of trees are planted at hospital campus. (Dt. 13.08.2021)
calendar August 2021
CE, PWD visited the site for monitoring quality and progress of construction works. (Dt. 14.08.2021).
calendar August 2021
75th Independence Day celebrated at the construction site. (dt. 15.08.2021)
calendar August 2021
The Medical Camp was conducted by the Hospital Authority to vaccinate the labours & staffs of the construction project. (Dt. 21.08.2021)
calendar August 2021
Site inspection by AEE, PWD on 25.08.2021
calendar August 2021
New PWD S.E. Er. Sathyamoorthi visit our site and he has planted trees in our site campus and we are held test for Fly ash brick in presence of SE. Test result for fly ash brick 8.65N/mm2 on 28.08.2021.
calendar September 2021
Earth backfilling and consolidation work started on 01.09.2021
calendar September 2021
The Quality Control team, PWD visited the site for monitoring the quality and progress of the construction works. (Dt. 02.09.2021)
calendar September 2021
Ramp area Ist flight slab reinforcement work under progress. (Dt. 03.09.2021)
calendar September 2021
Flooring P.C.C. work & HUME pipe laying work has been started on 06.09.2021.
calendar September 2021
Consultant team combining DTL, MEP Engineers has visited the site and discussed with PWD execution team / Contractor for MEP. (Dt. 08.09.2021)
calendar September 2021
The new EE, PWD visited the site for monitoring the quality and progress of the construction works. (Dt. 18.09.2021)
calendar September 2021
Meeting held with PWD, PMC & Contractor to expedite the ground floor slab concreting. (Dt. 23.09.2021)
calendar September 2021
Verifying of ground floor roof slab reinforcement work under progress. (Dt. 24.09.2021)
calendar September 2021
The Quality Control team, PWD visited the site for monitoring the quality and progress of the construction works. (Dt. 30.09.2021)

Work progress as on August 2021

calendar August 2021
Grade beam pouring concrete work under progress Dt. 01.08.2021
calendar August 2021
Steel reinforcement has been checked and Concrete pouring work for grade beam under progress Dt. 07.08.2021
calendar August 2021
Excavated earth back filling up to grade beam in completed areas under progress Dt. 11.08.2021
calendar August 2021
Brick work for basement walls up to DPC level work under progress Dt. 19.08.2021
calendar August 2021
Gravel filling work on basement wall constructed areas under progress Dt. 24.08.2021
calendar August 2021
Concrete pouring work for column lift up to roof level as grid X-axis 11 to 15, Y-axis 1.2 to 2.1 work under progress Dt. 31.08.2021

Work progress as on September 2021

calendar September 2021
Gravel filling and water consolidation work on basement wall constructed areas Dt. 02.09.2021
calendar September 2021
Hume laying work for rain water and sewage water from O.T.S to building outside Dt. 09.09.2021
calendar September 2021
Concrete pouring work for staircase first waist slab and landing Dt. 13.09.2021
calendar September 2021
Steel rods hoisting, placing & binding work for ground floor roof beams as grid X-axis 1 to 13, Y-axis 10 to 16 Dt. 20.09.2021
calendar September 2021
Form work for ground floor roof slab work under progress Dt. 23.09.2021
calendar September 2021
Reinforcement work under progress Dt. 29.09.2021
left-arrow Previous