TNHSP Logo
044-24345992 , 044-24335993 pdtnhsp@gmail.com
TNHSP Logo

Govt. Hospital Tiruppur

Home > Govt. Hospital Tiruppur

Government Hospital Velamapalayam, Tiruppur

calendar August 2021
Concrete pouring on footings completed. (Dt. 02.08.2021)
calendar August 2021
The Medical Camp was conducted by the Hospital Authority to vaccinate the labours & staffs of the construction project. (Dt. 04.08.2021)
calendar August 2021
Quality Control team, PWD visited the site for monitoring quality and progress of construction works. (Dt. 06.08.2021)
calendar August 2021
Discussion with AE, PWD & Nodal Officer. (Dt. 13.08.2021)
calendar August 2021
Detailed project display boards in Tamil & English language are provided in the site. (Dt. 14.08.2021)
calendar August 2021
Safety meeting conducted by the Consultants for the site labours. (Dt. 26.08.2021)
calendar September 2021
PWD Executive engineer general site visit and inspected Footing reinforcement works. (Dt. 08.09.2021)
calendar September 2021
Footings level concrete completed. (Dt. 11.09.2021)
calendar September 2021
As per the agreement conditions, Environmental tests taken 1. Ambient air quality test 2. Ambient noise level test 3. DG Static emission test. (Dt. 14.09.2021)
calendar September 2021
Newly posted Executive engineer & Assistant Executive engineers, PWD visited the site. (Dt. 18.09.2021)
calendar September 2021
Discussion points are : 1. Personal protective equipments 2. Workers welfare facilities 3. Job hazards and precautions. (Dt. 11.09.2021)
calendar September 2021
Safety training conducted by safety engineer for workers & supervisors 1.Fire fighting training. 2.Manual handling and material shifting. (Dt. 28.09.2021)
calendar September 2021
PWD quality control EE, AEE,AE visited the site. Some instructions given to the contractors to follow up. (Dt. 27.09.2021)

Work progress as on August 2021

calendar August 2021
Shuttering work for Footing Dt. 02.08.2021
calendar August 2021
UG sump base slab reinforcement work under progress Dt. 05.08.2021
calendar August 2021
Hard rock strata removal from foundation areas under progress Dt. 11.08.2021
calendar August 2021
UG static water tank with pump house wall shuttering work under progress Dt. 20.08.2021
calendar August 2021
Existing Building demolition work and Excavation work under progress Dt. 24.08.2021
calendar August 2021
Bar bending and rebar binding work for footing under progress Dt. 28.08.2021

Work progress as on September 2021

calendar September 2021
Footing marking with total station Dt. 01.09.2021
calendar September 2021
Raft footing bottom mat under progress Dt. 07.09.2021
calendar September 2021
RCC concrete pouring for footings (M25 Grade) CF6, F6, F8, F1, CF5, F3, F3, RF8 Completed Dt. 11.09.2021
calendar September 2021
Grade beam shuttering work under progress Dt. 18.09.2021
calendar September 2021
Curing work for all concrete surface under progress Dt. 23.09.2021
calendar September 2021
Grade beam pouring concrete work under progress Dt. 27.09.2021
left-arrow Previous