Government Coimbatore Medical College Hospital, Coimbatore

calendar August 2021
The Medical Camp was conducted by the Hospital Authority to vaccinate the labours & staffs of the construction project. (dt. 28.08.2021)
calendar August 2021
Safety meeting conducted by the Safety Engineer for the site labours. (dt. 25.08.2021)
calendar August 2021
Detailed project display boards in Tamil & English language are provided in the site. (dt. 14.08.2021)
calendar August 2021
75th Independence Day celebrated at the construction site. (dt. 15.08.2021)
calendar September 2021
The Quality Control team, EE, SDO PWD visited the site for monitoring the quality and progress of the construction works. (dt. 08.09.2021)
calendar September 2021
The EE & SDO PWD visited the site for monitoring the quality and progress of the construction works. (dt. 17.09.2021)
calendar September 2021
The SE & EE, PWD visited the site for monitoring the quality and progress of the construction works. (dt. 24.09.2021)
calendar September 2021
The Quality Control team / AE PWD visited the site for monitoring the quality and progress of the construction works. (dt. 30.09.2021)

Work progress as on August 2021

calendar August 2021
F8 Raft concrete work under progressDt. 03.08.2021
calendar August 2021
Earthwork filling under progress Dt. 07.08.2021
calendar August 2021
CF12 Raft concrete completed.Dt. 12.08.2021
calendar August 2021
RF5 column and lift wall Rebar work completedDt. 18.08.2021
calendar August 2021
Soil filling workunder progress Dt. 24.08.2021
calendar August 2021
CF1 & CF13 Raft concrete completed Dt. 28.08.2021

Work progress as on September 2021

calendar September 2021
Grade beam GB46, GB38, GB37, GB21A, GB29,shuttering work under progressDt. 01.09.2021
calendar September 2021
Raft concrete & Consolidation and levelling work under progressDt. 04.09.2021
calendar September 2021
Bed lift shear wall and column box fixing work under progressDt. 13.09.2021
calendar September 2021
Raft rebar work under progress Dt. 20.09.2021
calendar September 2021
Column concreting above grade beam under progress Dt. 23.09.2021
calendar September 2021
Brick work under progress Dt. 30.09.2021