TNHSP Logo
044-24345992 , 044-24335993 pdtnhsp@gmail.com
TNHSP Logo

GRH

Home > GRH

Government Rajaji Hospital, Madurai

calendar August 2021
JICA Representative - Site Visited on 03.08.2021
calendar August 2021
JICA Representative - Site Visited on 03.08.2021
calendar August 2021
Safety meeting conducted by the Safety Engineer for the site labours. (dt. 04.08.2021)
calendar August 2021
CE & EE, PWD visited the site for the discussions on the sump location. (dt. 13.08.2021)
calendar August 2021
Detailed project display boards in Tamil & English language are provided in the site. (dt. 14.08.2021)
calendar August 2021
75th Independence Day celebrated at the construction site. (dt. 15.08.2021)
calendar August 2021
The Quality Control team, PWD visited the site for monitoring the quality and progress of the construction works. (dt. 17.08.2021)
calendar August 2021
First Aid Training Programme conducted by GRH Hospital Authority to the Safety Engineers & Site Engineers. (dt. 18.08.2021)
calendar August 2021
Quality Control team, PWD visited the site for monitoring quality and progress of construction works. (dt. 24.08.2021)
calendar August 2021
The Medical Camp was conducted by the Hospital Authority to vaccinate the labourer & staff of the construction project. (dt. 28.08.2021)
calendar September 2021
From Mukesh & Associates - DTL Site inspection & progress review meeting on 07.09.21 & 08.09.21.
calendar September 2021
The Medical Camp was conducted by the Hospital Authority to vaccinate the labourer & staff of the construction project. (dt. 10.09.2021)
calendar September 2021
GF roof slab concrete partially achieved. (dt. 10.09.2021)
calendar September 2021
New EE, PWD - Er. AYYA SAMY has visited the site and reviewed the progress of work. (Dt. 16.09.2021)
calendar September 2021
EE, PWD has discussed with contractor for agreement related queries. (dt. 25.09.2021)
calendar September 2021
For site workers DPH conducted the General health check up. (dt. 29.09.2021)
calendar September 2021
Contractor discussed with Dean, clearance for road side shop hindrance. (Dt. 30.09.2021)

Work progress as on August 2021

calendar August 2021
Grade beam & Column, RCC wall form work & Basement level brick work,Staging work for GF-Roof slab Dt. 04.08.2021
calendar August 2021
RF-3 Grade beam rebar and column 1st lift form work Dt. 11.08.2021
calendar August 2021
Ramp slab first flight under progress Dt. 19.08.2021
calendar August 2021
Concrete work for GF-Roof slab shuttering and rebars work under progress Dt. 25.08.2021
calendar August 2021
Staircase form work under progress Dt. 27.08.2021
calendar August 2021
Ground floor roof slab concreting work under progress Dt. 29.08.2021

Work progress as on September 2021

calendar September 2021
GF roof slab concrete completed and curing work under progress Dt. 01.09.2021
calendar September 2021
FF Column 1st lift rebar work under progress Dt. 04.09.2021
calendar September 2021
GF roof slab concrete work Grid No: X1-X7.1 to Y4.1-Y8 Dt. 10.09.2021
calendar September 2021
GF Roof slab de-shuttering work under progress Grid no.: X1-X7.1 to Y1-Y3 Dt. 18.09.2021
calendar September 2021
Column concrete works - 6 Nos.Grid no: X6-Y12, Y11.1, X12-Y12.2, X6.1-Y11.1 Dt. 25.09.2021
calendar September 2021
Plinth level brick work & column 2nd lift from work under progress Dt. 30.09.2021
left-arrow Previous